Agenda Item
Meeting Date: 2/5/2020 - 4:00 PM
Category: Facilities
Type: Action
Subject: 20.4 Approve Change Order #24 for BRCO Constructors Agreement #17-24-14 for the Tahoe Lake Elementary School Modernization & Addition Project
District Goals and Beliefs:
Belief 1 - Students are the focus of all decisions
Enclosure: Board Staff Report - TLE-BRCO #17-24-14 CO#24
TLE - BRCO #17-24-14 CO#24
File Attachment:
Board Staff Report - TLE - BRCO #17-24-14 CO#24.pdf
TLE - BRCO #17-24-14 CO#24.pdf
Summary: Change Order #24 to the original agreement for BRCO Constructors captures the cost associated with revised downspout routing to address a design conflict and for other miscellaneous design items in conflict with the existing site conditions.
Funding: $61,653.00 from 2019 Certificates of Participation Funds
Recommendation: Approve Change Order #24 for BRCO Constructors Agreement #17-24-14 for the Tahoe Lake Elementary School Modernization & Addition project
Approvals:
Recommended By:
Signed By:
Jorge Rojas - Director of Facilities, Maintenance and Operations
Signed By:
Todd Rivera - Executive Director of Business Services
Signed By:
Robert Leri - Superintendent Chief Learning Officer
Vote Results:

Original Motion
Member Dianna Driller Moved, Member Kirsten Livak seconded to approve the Original motion 'Approve Change Order #24 for BRCO Constructors Agreement #17-24-14 for the Tahoe Lake Elementary School Modernization & Addition project'. Upon a Roll-Call Vote being taken, the vote was: Aye: 4 Nay: 0.
The motion Carried 4 - 0
   
Kirsten Livak     Yes
Kim Szczurek     Yes
Dianna Driller     Yes
Cristina Hennessey     Yes