Agenda Item
Meeting Date: 1/8/2020 - 4:30 PM
Category: Facilities
Type: Action
Subject: 16.4 Approve Change Order #14 for Sac Valley Electric, Inc. Agreement #17-24-12 for the Tahoe Lake Elementary School Modernization & Addition Project
District Goals and Beliefs:
Belief 1 - Students are the focus of all decisions
Enclosure: Board Staff Report
TLE - SVE #17-24-12 CO#14
File Attachment:
Board Staff Report - TLE- SVE #17-24-12 CO#14.pdf
TLE - SVE #17-24-12 CO#14.pdf
Summary: Change Order #14 to the original agreement for Sac Valley Electric captures the cost associated with the extended project schedule per Construction Change Directive #36.3. This change order includes costs for labor and material increases, extension of supervision staff, and miscellaneous general conditions. This change order also covers costs to reinstall new data cabling in Buildings C&D per RFI-1213 response and address other miscellaneous items not covered in the contract documents
Funding: $170,145.00 from 2019 Certificates of Participation Funds
Recommendation: Approve Change Order #14 for Sac Valley Electric, Inc. Agreement #17-24-12 for the Tahoe Lake Elementary School Modernization & Addition Project
Approvals:
Recommended By:
Signed By:
Jorge Rojas - Director of Facilities, Maintenance and Operations
Signed By:
Todd Rivera - Executive Director of Business Services
Signed By:
Robert Leri - Superintendent Chief Learning Officer
Vote Results:

Original Motion
Member Dianna Driller Moved, Member Kirsten Livak seconded to approve the Original motion 'Approve Change Order #14 for Sac Valley Electric, Inc. Agreement #17-24-12 for the Tahoe Lake Elementary School Modernization & Addition Project'. Upon a Roll-Call Vote being taken, the vote was: Aye: 5 Nay: 0.
The motion Carried 5 - 0
   
Gaylan Larson     Yes
Kirsten Livak     Yes
Kim Szczurek     Yes
Dianna Driller     Yes
Cristina Hennessey     Yes