Agenda Item
Meeting Date:
5/6/2020 - 4:30 PM  
Category:
Facilities  
Type:
Action  
Subject:
17.2 Approve Change Order #58 for Central Valley Environmental, Inc. Agreement #17-24-02 for the Tahoe Lake Elementary School Modernization & Addition ProjectModernization & Addition Project  
District Goals and Beliefs:
Belief 1 - Students are the focus of all decisions
 
Enclosure:
Staff Report
TLE - CVE #17-24-02 CO#58
 
File Attachment:
Board Staff Report - TLE-CVE #17-24-02 CO#58 - JR Final.pdf
TLE - CVE #17-24-02 CO#58.pdf
 
Summary:
Change Order #58 to the original agreement for Central Valley Environmental, Inc. captures the cost associated with abatement of asbestos-containing materials in Building D to install backing for cabinets per Construction Change Directive #86. This change order also captures the cost associated with abatement of asbestos flooring, removal of existing lead-glazed tiles from the corridor walls, and removal of lead paint from the Multi-Purpose Room door frames. These additional items were not covered in the original contract documents.  
Funding:
$66,808.00 from 2019 Certificates of Participation Funds  
Recommendation
Approve Change Order #58 for Central Valley Environmental, Inc. Agreement #17-24-02 for the Tahoe Lake Elementary School  
Approvals:
Recommended By:
Signed By:
Jorge Rojas - Director of Facilities, Maintenance and Operations
Signed By:  
Todd Rivera - Executive Director of Business Services
Signed By:  
Robert Leri - Superintendent Chief Learning Officer
 
Vote Results:

Original Motion
Member Dianna Driller Moved, Member Kirsten Livak seconded to approve the Original motion 'Approve Change Order #58 for Central Valley Environmental, Inc. Agreement #17-24-02 for the Tahoe Lake Elementary School'. Upon a Roll-Call Vote being taken, the vote was: Aye: 5 Nay: 0.
The motion Carried 5 - 0
   
Gaylan Larson     Yes
Kirsten Livak     Yes
Kim Szczurek     Yes
Dianna Driller     Yes
Cristina Hennessey     Yes